Issue the PO and watch the job update itself - Material Timeline and Procurement Scheduling - Conduit Help
HELP
Material Timeline and Procurement Scheduling

Issue the PO and watch the job update itself

Lesson 8 of 9 · Purchase Orders & Vendors

Purchase orders and material requirements are one loop. Issuing a PO moves every requirement on it to Ordered, stamps the vendor, and records the PO’s expected delivery as the requirement’s forecast. Receiving the PO in full moves those requirements to Delivered and sets the forecast to the day the receipt was recorded. Requirements that are not on the PO do not move.

  1. Send PO-2026-0091 to Denver Electric Supply.
  2. The panel and Romex now read Ordered. The breakers and trim kit did not move.
  3. Record receipt of every line on the PO.
  4. The panel and Romex now read Delivered, with the forecast delivery set to the receipt date.

PO loop: the real purchase order page above the job's material requirements. Sending the PO moves linked requirements to Ordered; receiving it moves them to Delivered.