Order-by deadlines and expected deliveries show on the calendar as their own chips, separate from job chips, so the office sees the material timeline next to the crew schedule. An overdue order-by chip is marked in the warning color.
- The 200A main panel has to be ordered by September 30.
- The trim kit's September 21 order deadline has passed and is marked overdue.
- Click the right arrow to move to October.
- The deliveries land October 5, the day before the Harper job on October 6.
Calendar: order-by and delivery chips for the Harper job in September and October 2026, next to the job chips.