Converting an accepted bid to a job seeds a material requirement for every material line on the bid. Labor lines (service items, or anything priced by the hour) and the generated travel line are skipped on purpose: they are billed, not ordered. If the same item appears in two sections of a sectioned bid, the quantities are summed into one requirement.
- Convert the accepted Harper bid to a job, confirming the proposed schedule when the dialog asks.
- Review the four material requirements the conversion seeded below the bid. The 16-hour labor line and the travel line were not seeded.
Bid conversion: converting an accepted bid creates the job and seeds one material requirement per material line, skipping labor and travel.