Plan each requirement on the job - Material Timeline and Procurement Scheduling - Conduit Help
HELP
Material Timeline and Procurement Scheduling

Plan each requirement on the job

Lesson 6 of 9 · Purchase Orders & Vendors

Each requirement carries three dates. Needed by defaults to the day before the job starts. Order by is needed-by minus the lead time for that item’s category or vendor, so a 5-day electrical item due on site October 5 has to be ordered by September 30. A requirement whose order-by date has passed is marked overdue. Use the status picker on any row to choose a status directly, including Awaiting Payment while the customer deposit clears, or the quick button to advance one step.

  1. Read the order-by and needed-by dates on each row. The custom trim kit has a 14-day lead time and is already overdue.
  2. Add a ground rod kit from Denver Electric Supply. Its dates are computed from the job start.
  3. Set the 200A main panel to Awaiting Payment with the status picker.
  4. Use the quick button to move the panel from Awaiting Payment to Ordered.

Material Requirements on Job detail: every requirement with its order-by and needed-by dates, overdue marker, status picker and quick advance.